My to-dos · Project controls lead · 3 drafts ready2 drafts ready1 draft readyAll decided · 09:52
CORR-0212Draft readyApproved
Contractor letter: extension of time, weather days
Agent: reply drafted. 2 of 6 days accepted, per clause 19.2 (Adverse weather) and the site diary.
Approved · sent to contractor · logged
DOC-0455Draft readyApproved
Method statement rev B, piling
Agent: 5 review comments, against the ITP and spec section 4.3.
Comment 3 reworded by Project controls lead · approved · returned to contractor
TQ-0398Draft readyApproved
Rebar cover, level 4 columns
Agent: answer drafted, 40 mm cover.
You: which clause sets the cover?
Agent: spec section 3.4.2, Table 3, and drawing S-204 rev C. Added to the answer.
Approved · sent · logged
Every item on your list already carries the work: the reply, the review comments, the answer, with the references. You approve, change a line, or ask.
You decide. You never start from a blank page.